It turned out to be a topic activity that had a predecessor! I ran the no-topic utility, and organized the schedule in suretrak in outline mode, then outdented everything. Now my RD is driving my EF.
Member for
22 years 10 months
Member for22 years10 months
Submitted by Ronald Winter on Fri, 2005-07-08 12:11
Member for
20 years 8 monthsRE: Bogus EF dates...
Go to Project Overview > check Project Must Finish By. If you imposed any finish date constraint, remove it and re-calculate the schedule.
Regards.
Member for
20 years 4 monthsRE: Bogus EF dates...
No, I checked all that.
It turned out to be a topic activity that had a predecessor! I ran the no-topic utility, and organized the schedule in suretrak in outline mode, then outdented everything. Now my RD is driving my EF.
Member for
22 years 10 monthsRE: Bogus EF dates...
Do you have an Expected Finish constraint posted for that activity?