Clarification on some points below:-



Jaroslava Sedrlova wrote:-My friend sent me project in pdf. There is no way to open a pdf as a workable schedule….you will need to get a PRX file…ask for a compressed backup or re-enter the data.



Alexandre Faulx-Briole and Sukumaran Subaramaniyan made good suggestions on breaking up the schedule however be careful.



With Alexandre’s method you will need to review the downstream constraints each time you reschedule one of the sections of the schedule.



With Sukumaran’s method you should break it so the relationships all flow one way ie from project 1 to project 2 then onto project 3 as you can then schedule the project in sequence once and the correct dates will be calculated. The moment you go back to an earlier project you would need to reschedule that project in the correct sequence to get valid dates on all activities.



Hope this helps.

Member for

20 years 8 months

Ask your friend forward to you the back up PRX file. You do not need to redo the schedule, just restore and work on it.



Check whether the message is still popping out. If yes, you split the schedule to a smaller workpackages and create a project group template.



Using project group template copy the smaller workpackages as a subproject and interlink the related activities. With project group you can manage all the workpackages simultaneously and efficiently. This might help you to solve the problem.



For more info go to help and read through the Project Groups.



Regards.

Member for

22 years 9 months

Jaroslav,

ask somebody with a full P3 to split your 200 task project in 4 smaller workpackages

the links between them will be replaced by Start Not Earlier Than dates.

This will work fine

Alexandre

Member for

20 years 6 months

Hi.

I don’t think that it’s my case. The project has less than 200 activities. My friend sent me project in pdf. I can see the result but I can’t see information what I need for my bachelor

work.

If anybody can help me I will be very happy.

Have a nice day.

Member for

20 years 9 months

Another thing is that P3 has limitation for showing activities more than 32000 and it recommends applying filters to select group of activities. Please make sure this is not your case.

Member for

20 years 6 months

Hi.

Can anybody do it for me, please? Make smaller workpackages?

Will information about precedessor be the same? Actually I need only this information from the file.

Thank you.



My number is 9791.

Member for

22 years 9 months

To use any commercial application without a proper license is robbery!

If your planning exceeds the maximum possible for the evaluation copy of P3, you could ask someone with a full P3 to split the project in smaller workpackages (not fragnets) that you will open separately.

As a PM instructor, I use a eval copy of P3 and that’s the way I am working

Regards

Member for

20 years 6 months

Hi.

You were right. I need license. I need just open one file. Is there any other chance how I can do it without license?

Anyway. Thank you.

Jarka

Member for

20 years 8 months

I’m using the license copy. My project activities have exceeded 23,000. Hence with the license programme I’m having the same problem as Jaroslava.



May be it is an installation problem. If you got the CD try to re-install with full installation.



Regards.

Member for

22 years 7 months

Hi Jaroslava,

It should be demo version which you are using, hence you have to buy a P3 with license, then you can work well.

Cheers!!!

Daya

Member for

20 years 11 months

Hi there.

Probably it’s mere evaluation version of P3.

Member for

22 years 9 months

Hi,

Do you have a full P3 license or an evaluation copy limited to 60 activity rows?

Alexandre