What I understand is that in Tools > Tabular or graphical reports, all reports are based on either cost or quantity.
Assume that my schedule is not cost or resource (Qty) loaded. I can not use any tabluar or graphical report!! My schedule contains only activities and I want to develop Early and Late S curves for the planned % comp.
My progress measurment will only be based on Tools > Options > Summarization > Duration.
May be I was unable to explain my querry properly.
Member for
21 years 2 months
Member for21 years2 months
Submitted by Jaco Stadler on Sat, 2004-12-18 03:56
Well, as long as I am able to get the data (could be a column inside the P3 schedule) I can export it to Xcel. My objective is to get % late comp for each activity that can be summarized to an overall % comp. . . .
Member for
21 years 2 months
Member for21 years2 months
Submitted by Jaco Stadler on Sat, 2004-12-18 03:28
Member for
21 years 2 monthsRE: Planned % comp based on Late dates.
Daya I agree with you. Thanx Eric for you tip!! It really worked . .
Member for
22 years 7 monthsRE: Planned % comp based on Late dates.
Follow Eriks advice; it would be easier to introduce a dummy resource to accomplish your task.
Member for
22 years 6 monthsRE: Planned % comp based on Late dates.
Hi Muhammad,
The only way to do this would be to create a duration resource.
The easiest way would be to add a resource called time and set the budget quantity equal to the original duration.
You would then be able to do an s-curve.
Regards,
Erik
Member for
21 years 2 monthsRE: Planned % comp based on Late dates.
What I understand is that in Tools > Tabular or graphical reports, all reports are based on either cost or quantity.
Assume that my schedule is not cost or resource (Qty) loaded. I can not use any tabluar or graphical report!! My schedule contains only activities and I want to develop Early and Late S curves for the planned % comp.
My progress measurment will only be based on Tools > Options > Summarization > Duration.
May be I was unable to explain my querry properly.
Member for
21 years 2 monthsRE: Planned % comp based on Late dates.
The Easy Way is to export the summary the report I found the easiast is Tools / Tabluar Report / Tabular / RT1.
You modify this report (Or copy) Then you Export You Can Select Which Dates you want to export on this (Timescale)
Hope this help
Member for
21 years 2 monthsRE: Planned % comp based on Late dates.
Well, as long as I am able to get the data (could be a column inside the P3 schedule) I can export it to Xcel. My objective is to get % late comp for each activity that can be summarized to an overall % comp. . . .
Member for
21 years 2 monthsRE: Planned % comp based on Late dates.
Do you want to show the percentage in a Column on the schedule or on the S-Curve