Planned % comp based on Late dates.

Member for

22 years 7 months

Follow Erik’s advice; it would be easier to introduce a dummy resource to accomplish your task.


Member for

22 years 6 months

Hi Muhammad,



The only way to do this would be to create a duration resource.



The easiest way would be to add a resource called time and set the budget quantity equal to the original duration.



You would then be able to do an s-curve.



Regards,



Erik

Member for

21 years 2 months

What I understand is that in Tools > Tabular or graphical reports, all reports are based on either cost or quantity.



Assume that my schedule is not cost or resource (Qty) loaded. I can not use any tabluar or graphical report!! My schedule contains only activities and I want to develop Early and Late S curves for the planned % comp.



My progress measurment will only be based on Tools > Options > Summarization > Duration.



May be I was unable to explain my querry properly.

Member for

21 years 2 months

The Easy Way is to export the summary the report I found the easiast is Tools / Tabluar Report / Tabular / RT1.



You modify this report (Or copy) Then you Export You Can Select Which Dates you want to export on this (Timescale)



Hope this help

Member for

21 years 2 months

Well, as long as I am able to get the data (could be a column inside the P3 schedule) I can export it to Xcel. My objective is to get % late comp for each activity that can be summarized to an overall % comp. . . .

Member for

21 years 2 months

Do you want to show the percentage in a Column on the schedule or on the S-Curve