When I am managing serious projects I calculate 4 percent completes:
1. The % of the original duration
2. The % of deliverables completed
3. The % of cost expended
4. The % of hours of labour or mobile equipment consumed
The comparison of the four percentage completes is very useful.
I normally use the P3 % complete for the % of duration, unlink % Complete and Remaining Duration and turn off all the Autocost Rules, I may enter the recorded cost and hours consumed and estimated to complete.
I use global changes to calculate the other three in custom data items.
There is an article titles The Practical Application of Earned Value which is on my web site which outlines some of these techniques.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
Member for
24 years 6 monthsRE: Total Planned % complete formula
When I am managing serious projects I calculate 4 percent completes:
1. The % of the original duration
2. The % of deliverables completed
3. The % of cost expended
4. The % of hours of labour or mobile equipment consumed
The comparison of the four percentage completes is very useful.
I normally use the P3 % complete for the % of duration, unlink % Complete and Remaining Duration and turn off all the Autocost Rules, I may enter the recorded cost and hours consumed and estimated to complete.
I use global changes to calculate the other three in custom data items.
There is an article titles The Practical Application of Earned Value which is on my web site which outlines some of these techniques.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Member for
16 years 9 monthsRE: Total Planned % complete formula
[(sum of OD’s - sum of RD’s)/(Sum of OD’s)]*100 <---you missed it.
cheers
Member for
23 years 8 monthsRE: Total Planned % complete formula
According to Primavera KnowledgeBase 1999492110554, the formula is: -
(sum of ODs - sum of RDs)/(Sum of ODs)