Total Planned % complete formula

Member for

24 years 6 months

When I am managing serious projects I calculate 4 percent completes:



1. The % of the original duration

2. The % of deliverables completed

3. The % of cost expended

4. The % of hours of labour or mobile equipment consumed



The comparison of the four percentage completes is very useful.



I normally use the P3 % complete for the % of duration, unlink % Complete and Remaining Duration and turn off all the Autocost Rules, I may enter the recorded cost and hours consumed and estimated to complete.



I use global changes to calculate the other three in custom data items.



There is an article titles The Practical Application of Earned Value which is on my web site which outlines some of these techniques.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

Member for

16 years 9 months

[(sum of OD’s - sum of RD’s)/(Sum of OD’s)]*100 <---you missed it.

cheers

Member for

23 years 8 months

According to Primavera KnowledgeBase 1999492110554, the formula is: -

(sum of OD’s - sum of RD’s)/(Sum of OD’s)