...or maybe you may make a copy of the "resource levelled" scheduled and use it as a Target 1 (or 2). Then you can prepare a layout comparing that Target against your current schedule.
Member for
22 years 11 months
Member for23 years
Submitted by Steven Oliver on Mon, 2003-11-17 10:09
Try creating a custom data item to hold the levelled value of early start, and after re-scheduling set the early start constraint equal to the custom data item
Member for
22 years 3 monthsRE: LEVELLING OF RESOURCE
You can run a Global Change to automatically constrain the leveled early start dates:
Create a new Global Change statement and in the Then area, write:
SNE EQ ES
This should work.
regards,
Jorge Taguinod
Member for
22 years 5 monthsRE: LEVELLING OF RESOURCE
THXS A LOT.
Member for
24 years 3 monthsRE: LEVELLING OF RESOURCE
...or maybe you may make a copy of the "resource levelled" scheduled and use it as a Target 1 (or 2). Then you can prepare a layout comparing that Target against your current schedule.
Member for
22 years 11 monthsRE: LEVELLING OF RESOURCE
Try creating a custom data item to hold the levelled value of early start, and after re-scheduling set the early start constraint equal to the custom data item