LEVELLING OF RESOURCE

Member for

22 years 3 months

You can run a Global Change to automatically constrain the leveled early start dates:



Create a new Global Change statement and in the Then area, write:



SNE EQ ES



This should work.



regards,



Jorge Taguinod

Member for

24 years 3 months

...or maybe you may make a copy of the "resource levelled" scheduled and use it as a Target 1 (or 2). Then you can prepare a layout comparing that Target against your current schedule.

Member for

22 years 11 months

Try creating a custom data item to hold the levelled value of early start, and after re-scheduling set the early start constraint equal to the custom data item