Linking of P3 data base to AutoCad.

Member for

23 years 8 months

In P3, filter out those activities which will be in chainage diagram by code.



In autocad, prepare a macro including: -

- link to P3 selected activities and look for activity type, duration and dates.

- prepare the axis of the diagram, ie time scale and chainage scale

- shape of each object determine by activity type

- size of the polygon depends by dates and duration

- for color, may by some activity code



MKTSE