Primavera Project Planner - P3 Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Wed, 2003-10-15 10:37 Permalink RE: Linking of P3 data base to AutoCad. In P3, filter out those activities which will be in chainage diagram by code. In autocad, prepare a macro including: - - link to P3 selected activities and look for activity type, duration and dates. - prepare the axis of the diagram, ie time scale and chainage scale - shape of each object determine by activity type - size of the polygon depends by dates and duration - for color, may by some activity code MKTSE Log in or register to post comments
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Wed, 2003-10-15 10:37 Permalink RE: Linking of P3 data base to AutoCad. In P3, filter out those activities which will be in chainage diagram by code. In autocad, prepare a macro including: - - link to P3 selected activities and look for activity type, duration and dates. - prepare the axis of the diagram, ie time scale and chainage scale - shape of each object determine by activity type - size of the polygon depends by dates and duration - for color, may by some activity code MKTSE
Member for
23 years 8 monthsRE: Linking of P3 data base to AutoCad.
In P3, filter out those activities which will be in chainage diagram by code.
In autocad, prepare a macro including: -
- link to P3 selected activities and look for activity type, duration and dates.
- prepare the axis of the diagram, ie time scale and chainage scale
- shape of each object determine by activity type
- size of the polygon depends by dates and duration
- for color, may by some activity code
MKTSE