Filter Specification

Member for

22 years 5 months

What I mean to say are on going Activities (% comp. > 0) which started late.

Member for

22 years 6 months

How can a activity that has not started have +ve%, please explain

Member for

22 years 5 months

Yes I agree with you Joel if we are reffering to delays on dates, but if we consider %wise this is not applicable. Sometime some activities are late in early start but %wise +ve.

Member for

22 years 6 months

If I understand your question correctly you want to track difference between base start/finish and schedule start./finish and what is running behind with the aid of a filter. Hoping this will help.

For activities behind schedule use variance target 1 early start LT 0 in your filter and variance target 1 early finish LT 0 in your filter depending if you want to track start or finish delays

Member for

22 years 5 months

I think its possible by adding costum data item. then use the import and export option.

Member for

16 years 9 months

There is no filter specification for Tar1 or Tar 2 % Complete thats why you cant make such filter. I suggest you follow the steps outlined by Jorge.



Se

Member for

22 years 5 months

Pareng Jorge, How can we filter activities with Schedule % >0 (or percent in your Target)and Actual % > 0.



PCT_T1 > 0 and PCT > 0 In one Layout


Member for

22 years 3 months

Quite easy.



1. Create a second Target project by copying the original target.

2. Close Current Schedule and Open Target 2.

3. Update Target 2 to Data Date using Tools, Update Progress. Select All Activities. This creates the Planned Percent complete.

4. Close Target 2 and Open Current Project.

5. Add the following Columns in the layout: Percent Complete and Target 2 Percent Complete.



Viola! You can now compare Planned Percent Complete and Current Percent Complete.



Note: You need to update Target 2 using Update Progress command using the latest Data Date everytime you want this layout.



Jorge

Member for

24 years 9 months

You can do the following steps to specify the required filter (make the progressed project as current and planned project as a target)



1- creat custom data item as start date and finish date

(default in p3 PLST and PLF



2- creat global change the custum data start = taget1 early start and finish date = target 1 early finish



Then:

PLST = T1ES

PLFN = T1EF



3- in the filter specify that:



PLST WR (specify the required date)



ES WR (specify samedate)







I hope this solve your problem,



egards,



Khalid Abdelaal