What I mean to say are on going Activities (% comp. > 0) which started late.

Member for

22 years 6 months

How can a activity that has not started have +ve%, please explain

Member for

22 years 5 months

Yes I agree with you Joel if we are reffering to delays on dates, but if we consider %wise this is not applicable. Sometime some activities are late in early start but %wise +ve.

Member for

22 years 6 months

If I understand your question correctly you want to track difference between base start/finish and schedule start./finish and what is running behind with the aid of a filter. Hoping this will help.

For activities behind schedule use variance target 1 early start LT 0 in your filter and variance target 1 early finish LT 0 in your filter depending if you want to track start or finish delays

Member for

22 years 5 months

I think its possible by adding costum data item. then use the import and export option.

Member for

16 years 9 months

There is no filter specification for Tar1 or Tar 2 % Complete thats why you cant make such filter. I suggest you follow the steps outlined by Jorge.



Se

Member for

22 years 5 months

Pareng Jorge, How can we filter activities with Schedule % >0 (or percent in your Target)and Actual % > 0.



PCT_T1 > 0 and PCT > 0 In one Layout


Member for

22 years 4 months

Quite easy.



1. Create a second Target project by copying the original target.

2. Close Current Schedule and Open Target 2.

3. Update Target 2 to Data Date using Tools, Update Progress. Select All Activities. This creates the Planned Percent complete.

4. Close Target 2 and Open Current Project.

5. Add the following Columns in the layout: Percent Complete and Target 2 Percent Complete.



Viola! You can now compare Planned Percent Complete and Current Percent Complete.



Note: You need to update Target 2 using Update Progress command using the latest Data Date everytime you want this layout.



Jorge

Member for

24 years 10 months

You can do the following steps to specify the required filter (make the progressed project as current and planned project as a target)



1- creat custom data item as start date and finish date

(default in p3 PLST and PLF



2- creat global change the custum data start = taget1 early start and finish date = target 1 early finish



Then:

PLST = T1ES

PLFN = T1EF



3- in the filter specify that:



PLST WR (specify the required date)



ES WR (specify samedate)







I hope this solve your problem,



egards,



Khalid Abdelaal