Planning & Programming Training Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Tue, 2010-01-05 05:02 Permalink RE: Programme for Fuel Storage Tanks in Afghanistan Youd also need a bund, and a fire fighting system. Depending on the fuel type, the tanks may be fixed roof, floating roof, or fixed roof with internal floating roof. Allow time for cleaning out the tank after construction. Commissioning will usually comprise of water test, and a fuel soak test. (plus usual commissioning of associated pipes, pumps, FFS, etc) Member for 17 years 3 months Member for 17 years 3 months Submitted by Samer Zawaydeh on Mon, 2009-12-28 00:23 Permalink RE: Programme for Fuel Storage Tanks in Afghanistan Dear Alan, You might want to add the following sections as well: I. Shop Drawings Submittals. II. Material Submittals. a. The Inspection and Test Plan is a major Quality Document that you need to get it submitted and agree with the client and the Engineer. III. Procurement. This is Major item that you want to study. Exactly how to Fabricate/ Paint/ Deliver the material to site. IV. Installation: a. Add a line item for Anchor Bolts. b. NDT testing is done at site. c. Add the Electro Mechanical Activities d. You need a lot of scafolding depending on the size. V. Security is a major item. decide what you need and if it is related to your construction sequence. VI. Testing Decide what testing is required depending on your specifications and add it as activities with the right sequence. VII. Quality Control Documents. Decide what you need and add them as activities. With kind regards, Samer Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Sun, 2009-12-27 04:48 Permalink RE: Programme for Fuel Storage Tanks in Afghanistan Hi it is just a sample for storage tanks Activity description Excavation Blinding Formwork/Steel Reinf. - Base RCC Casting - Base Waterproofing Base Dune Sand Filling External Backfilling Placement & Welding of Steel Base Plate Welding & erection of Steel Shell & Roof Testing and Inspection Paint Primer works Final Paint works Piping and Connection to Steel Tanks Installation of Water Meters Piping and Connection to main Building Log in or register to post comments
Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Tue, 2010-01-05 05:02 Permalink RE: Programme for Fuel Storage Tanks in Afghanistan Youd also need a bund, and a fire fighting system. Depending on the fuel type, the tanks may be fixed roof, floating roof, or fixed roof with internal floating roof. Allow time for cleaning out the tank after construction. Commissioning will usually comprise of water test, and a fuel soak test. (plus usual commissioning of associated pipes, pumps, FFS, etc)
Member for 17 years 3 months Member for 17 years 3 months Submitted by Samer Zawaydeh on Mon, 2009-12-28 00:23 Permalink RE: Programme for Fuel Storage Tanks in Afghanistan Dear Alan, You might want to add the following sections as well: I. Shop Drawings Submittals. II. Material Submittals. a. The Inspection and Test Plan is a major Quality Document that you need to get it submitted and agree with the client and the Engineer. III. Procurement. This is Major item that you want to study. Exactly how to Fabricate/ Paint/ Deliver the material to site. IV. Installation: a. Add a line item for Anchor Bolts. b. NDT testing is done at site. c. Add the Electro Mechanical Activities d. You need a lot of scafolding depending on the size. V. Security is a major item. decide what you need and if it is related to your construction sequence. VI. Testing Decide what testing is required depending on your specifications and add it as activities with the right sequence. VII. Quality Control Documents. Decide what you need and add them as activities. With kind regards, Samer
Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Sun, 2009-12-27 04:48 Permalink RE: Programme for Fuel Storage Tanks in Afghanistan Hi it is just a sample for storage tanks Activity description Excavation Blinding Formwork/Steel Reinf. - Base RCC Casting - Base Waterproofing Base Dune Sand Filling External Backfilling Placement & Welding of Steel Base Plate Welding & erection of Steel Shell & Roof Testing and Inspection Paint Primer works Final Paint works Piping and Connection to Steel Tanks Installation of Water Meters Piping and Connection to main Building
Member for
16 years 7 monthsRE: Programme for Fuel Storage Tanks in Afghanistan
Youd also need a bund, and a fire fighting system.
Depending on the fuel type, the tanks may be fixed roof, floating roof, or fixed roof with internal floating roof.
Allow time for cleaning out the tank after construction.
Commissioning will usually comprise of water test, and a fuel soak test. (plus usual commissioning of associated pipes, pumps, FFS, etc)
Member for
17 years 3 monthsRE: Programme for Fuel Storage Tanks in Afghanistan
Dear Alan,
You might want to add the following sections as well:
I. Shop Drawings Submittals.
II. Material Submittals.
a. The Inspection and Test Plan is a major Quality Document that you need to get it submitted and agree with the client and the Engineer.
III. Procurement. This is Major item that you want to study. Exactly how to Fabricate/ Paint/ Deliver the material to site.
IV. Installation:
a. Add a line item for Anchor Bolts.
b. NDT testing is done at site.
c. Add the Electro Mechanical Activities
d. You need a lot of scafolding depending on the size.
V. Security is a major item. decide what you need and if it is related to your construction sequence.
VI. Testing
Decide what testing is required depending on your specifications and add it as activities with the right sequence.
VII. Quality Control Documents.
Decide what you need and add them as activities.
With kind regards,
Samer
Member for
16 years 11 monthsRE: Programme for Fuel Storage Tanks in Afghanistan
Hi it is just a sample for storage tanks
Activity description
Excavation
Blinding
Formwork/Steel Reinf. - Base
RCC Casting - Base
Waterproofing Base
Dune Sand Filling
External Backfilling
Placement & Welding of Steel Base Plate
Welding & erection of Steel Shell & Roof
Testing and Inspection
Paint Primer works
Final Paint works
Piping and Connection to Steel Tanks
Installation of Water Meters
Piping and Connection to main Building