Programme for Fuel Storage Tanks in Afghanistan

Member for

16 years 7 months

You’d also need a bund, and a fire fighting system.



Depending on the fuel type, the tanks may be fixed roof, floating roof, or fixed roof with internal floating roof.



Allow time for cleaning out the tank after construction.



Commissioning will usually comprise of water test, and a fuel soak test. (plus usual commissioning of associated pipes, pumps, FFS, etc)

Member for

17 years 3 months

Dear Alan,



You might want to add the following sections as well:



I. Shop Drawings Submittals.



II. Material Submittals.

a. The Inspection and Test Plan is a major Quality Document that you need to get it submitted and agree with the client and the Engineer.



III. Procurement. This is Major item that you want to study. Exactly how to Fabricate/ Paint/ Deliver the material to site.



IV. Installation:

a. Add a line item for Anchor Bolts.

b. NDT testing is done at site.

c. Add the Electro Mechanical Activities

d. You need a lot of scafolding depending on the size.



V. Security is a major item. decide what you need and if it is related to your construction sequence.



VI. Testing

Decide what testing is required depending on your specifications and add it as activities with the right sequence.



VII. Quality Control Documents.

Decide what you need and add them as activities.



With kind regards,



Samer

Member for

16 years 11 months



Hi it is just a sample for storage tanks

Activity description

Excavation

Blinding

Formwork/Steel Reinf. - Base

RCC Casting - Base

Waterproofing Base

Dune Sand Filling

External Backfilling

Placement & Welding of Steel Base Plate

Welding & erection of Steel Shell & Roof

Testing and Inspection

Paint Primer works

Final Paint works

Piping and Connection to Steel Tanks

Installation of Water Meters

Piping and Connection to main Building