Hospital project..

Member for

16 years 7 months

Ahmed:



Roland requested you send him a private message, rather post your request here.



To do this, just click on the blue envelope next to his name.



Cheers,



G

Member for

16 years

I guess i am a bit too late.. but if someone still needs some guidance into planning a hospital, i have a pdf file which illustrates the baseline schedule of a hospital project which was shared by some planner on another forum. So please if you need a copy just send me a private message on PP.

Regards.

Member for

16 years 8 months

I am sorry about your situation. I hope as less time you can do it.If you will achieve sample project plan which made by p6, pls don’t forget me. May it be easy

Best Regards

Member for

17 years 1 month

Hello Cihangir,



Our scope of works in this hospital project has been changed from design and built to Phase I - Piling works...

So as of this time, piling works is still in progress and expected to finish by mid of October.



Samer suggestions on how to prepare a plan can help, as the baseline depends on project scope of works, milestones and deliverables.



Best regards,

Sandy

Member for

16 years 8 months

Hi Sandy,

how is going your project? i hope every thing fine. My firm take a new hospital project now. and i need hand to about planning (P6). if you can send me your project plan, i will glad you.

Thanks a lot

Member for

18 years 6 months



Thanks Samer..

Member for

18 years 6 months

Hi Samer,



Can I have a copy of P6 Manual. My email is p3-fer@sixco.ae



Thanks in advance.

Member for

17 years 5 months

Thanks Samer

I received it.



Ashutosh Nema

Member for

17 years 1 month

Thanks a lot Samer, I received it!



Cheers!

Sandy

Member for

17 years 5 months

Dear Samer

Can you please send me the copy of P-6 mannual,I am also using P-6 in my multi-story project.I have P-5 mannual.



Thanks for sharing.My mail Id is ashutoshnema19@gmail.com



Ashutosh Nema

Member for

17 years 3 months

Dear Sandy,



You are most welcome, if you need a soft copy of P6 manual, please sent me your email.



Good luck,



Samer

Member for

17 years 1 month

Thank you Samer...

As of this time, dont have any specific question yet. And by the way we will be using primavera P6 in this project. Another ’first time’ to me. But will attend a crash course this week.



Best regards,

Sandy










Member for

17 years 3 months

Dear Sandy,



Let me suggest that you start out by reviewing the Contract documents with your team.



1. Divide the project into its main parts. Read a bit about Work Break Down Structure.



2. Start working toward defining the activities required for each Zone or part.



3. Start defining the duration and resources required for each activity.



4. Link the activities together.



If you have more specific questions, please ask.



Good luck.



sAmer