I guess i am a bit too late.. but if someone still needs some guidance into planning a hospital, i have a pdf file which illustrates the baseline schedule of a hospital project which was shared by some planner on another forum. So please if you need a copy just send me a private message on PP.
Regards.
Member for
16 years 8 months
Member for16 years9 months
Submitted by Cihangir Basbug on Sat, 2009-08-29 05:00
I am sorry about your situation. I hope as less time you can do it.If you will achieve sample project plan which made by p6, pls dont forget me. May it be easy
Best Regards
Member for
17 years 1 month
Member for17 years2 months
Submitted by Sandy Sandoval on Sat, 2009-08-29 02:32
how is going your project? i hope every thing fine. My firm take a new hospital project now. and i need hand to about planning (P6). if you can send me your project plan, i will glad you.
Thanks a lot
Member for
17 years 1 month
Member for17 years1 month
Submitted by abdesalam obeidat on Sat, 2008-09-27 11:49
As of this time, dont have any specific question yet. And by the way we will be using primavera P6 in this project. Another first time to me. But will attend a crash course this week.
Best regards,
Sandy
Member for
17 years 3 months
Member for17 years3 months
Submitted by Samer Zawaydeh on Fri, 2008-09-19 10:26
Member for
16 years 7 monthsRE: Hospital project..
Ahmed:
Roland requested you send him a private message, rather post your request here.
To do this, just click on the blue envelope next to his name.
Cheers,
G
Member for
16 years 5 monthsRE: Hospital project..
can i have copy my email ahmedfawzy91@hotmail.com
Member for
16 yearsRE: Hospital project..
I guess i am a bit too late.. but if someone still needs some guidance into planning a hospital, i have a pdf file which illustrates the baseline schedule of a hospital project which was shared by some planner on another forum. So please if you need a copy just send me a private message on PP.
Regards.
Member for
16 years 8 monthsRE: Hospital project..
I am sorry about your situation. I hope as less time you can do it.If you will achieve sample project plan which made by p6, pls dont forget me. May it be easy
Best Regards
Member for
17 years 1 monthRE: Hospital project..
Hello Cihangir,
Our scope of works in this hospital project has been changed from design and built to Phase I - Piling works...
So as of this time, piling works is still in progress and expected to finish by mid of October.
Samer suggestions on how to prepare a plan can help, as the baseline depends on project scope of works, milestones and deliverables.
Best regards,
Sandy
Member for
16 years 8 monthsRE: Hospital project..
Hi Sandy,
how is going your project? i hope every thing fine. My firm take a new hospital project now. and i need hand to about planning (P6). if you can send me your project plan, i will glad you.
Thanks a lot
Member for
17 years 1 monthRE: Hospital project..
Can I have a copy plaease too
abdesalam@gmail.com
thanx
Member for
18 years 6 monthsRE: Hospital project..
Thanks Samer..
Member for
17 years 1 monthRE: Hospital project..
Samer,
Please send me too a soft copy of P6. My email julespina@yahoo.com
Thanks.
Julius
Member for
18 years 6 monthsRE: Hospital project..
Hi Samer,
Can I have a copy of P6 Manual. My email is p3-fer@sixco.ae
Thanks in advance.
Member for
17 years 5 monthsRE: Hospital project..
Thanks Samer
I received it.
Ashutosh Nema
Member for
17 years 1 monthRE: Hospital project..
Thanks a lot Samer, I received it!
Cheers!
Sandy
Member for
17 years 5 monthsRE: Hospital project..
Dear Samer
Can you please send me the copy of P-6 mannual,I am also using P-6 in my multi-story project.I have P-5 mannual.
Thanks for sharing.My mail Id is ashutoshnema19@gmail.com
Ashutosh Nema
Member for
17 years 3 monthsRE: Hospital project..
Dear Sandy,
You are most welcome, if you need a soft copy of P6 manual, please sent me your email.
Good luck,
Samer
Member for
17 years 1 monthRE: Hospital project..
Thank you Samer...
As of this time, dont have any specific question yet. And by the way we will be using primavera P6 in this project. Another first time to me. But will attend a crash course this week.
Best regards,
Sandy
Member for
17 years 3 monthsRE: Hospital project..
Dear Sandy,
Let me suggest that you start out by reviewing the Contract documents with your team.
1. Divide the project into its main parts. Read a bit about Work Break Down Structure.
2. Start working toward defining the activities required for each Zone or part.
3. Start defining the duration and resources required for each activity.
4. Link the activities together.
If you have more specific questions, please ask.
Good luck.
sAmer