Incorrect Duration % Complete value at WBS level

Member for

16 years 3 months

glad I could help 

Member for

5 years 6 months

Thanks Zoltan!

Member for

19 years

Duration % Complete = percent complete of the activity duration.

Formula = (Original Duration - Remaining Duration)/Original Duration * 100.

Note: Original Duration is taken from the current plan, not from the baseline.

Member for

16 years 3 months

That is correct.

However

The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far

Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP • 100) I BAC, regardless of what earned value technique is selected for the activity's WBS.

 
You could create a LOE activity that spans from the 1st activity (SS) in that wbs to the last actvitiy (FF) in that wbs and look at it that way. The the duration % complete would then be correct beciase it is considering the entire tiem frame not just individual activities.
 
The other thing to do is to create a new activity and give the ACTIVITY TYPE AS WBS SUMMARY AND IT WILL DO THE SAME THINGS AS A LOE type of activitiy.