The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far
Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP • 100) I BAC, regardless of what earned value technique is selected for the activity's WBS.
You could create a LOE activity that spans from the 1st activity (SS) in that wbs to the last actvitiy (FF) in that wbs and look at it that way. The the duration % complete would then be correct beciase it is considering the entire tiem frame not just individual activities.
The other thing to do is to create a new activity and give the ACTIVITY TYPE AS WBS SUMMARY AND IT WILL DO THE SAME THINGS AS A LOE type of activitiy.
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
5 years 6 monthsThanks Zoltan!
Thanks Zoltan!
Member for
19 yearsDuration % Complete = percent
Duration % Complete = percent complete of the activity duration.
Formula = (Original Duration - Remaining Duration)/Original Duration * 100.
Note: Original Duration is taken from the current plan, not from the baseline.
Member for
16 years 3 monthsThat is correct.HoweverThe
That is correct.
However
The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far
Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP • 100) I BAC, regardless of what earned value technique is selected for the activity's WBS.