i will explain more i updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021
thats mean 15 days working day which give me increase at the total flot by -18 days and if i decresed the remaning duration for certain activites the total flot increase also to become -20
Member for
4 years 8 months
Member for4 years8 months
Submitted by mohammedusamaa on Thu, 2021-02-18 06:58
i will explain more i updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021
thats mean 15 days working day which give me increase at the total flot by -18 days and if i decresed the remaning duration for certain activites the total flot increase also to become -20
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Wed, 2021-02-17 14:56
Member for
21 years 8 months20,000 activities schedule is
20,000 activities schedule is for an experienced scheduler.
Are you updating the schedule or you mean revising current schedule version?
Member for
16 years 3 months1. 1st update the activites
1. 1st update the activites that have started with actul start dates but not finished and put in the remaining duration for each of those
2. If activites here started before and have now finished put in the actual start date.
3. If an activity has started AND finished put in the actual start AND actual finsh date
4. Press F9
5. Chnaae the dated date to reflect the date that you are recording progress thru
6. Analyse results
Member for
4 years 8 monthsi,m updating it i changed
i,m updating it
i changed the data date also
i will explain more i updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021
thats mean 15 days working day which give me increase at the total flot by -18 days and if i decresed the remaning duration for certain activites the total flot increase also to become -20
Member for
4 years 8 monthsi,m updating it i changed
i,m updating it
i changed the data date also
i will explain more i updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021
thats mean 15 days working day which give me increase at the total flot by -18 days and if i decresed the remaning duration for certain activites the total flot increase also to become -20
Member for
16 years 3 monthsare you changing the data
are you changing the data date also ?