help : activities total float is increasing by decreasing the remaining duration for the activates

Member for

21 years 8 months

20,000 activities schedule is for an experienced scheduler.

Are you updating the schedule or you mean revising current schedule version?

Member for

16 years 3 months

1. 1st update the activites that have started with actul start dates but not finished and put in the remaining duration for each of those

2. If activites here started before and have now finished put in the actual start date.

3. If an activity has started AND finished put in the actual start AND actual finsh date 

4. Press F9

5. Chnaae the dated date to reflect the date that you are recording progress thru

6. Analyse results

Member for

4 years 8 months

i,m updating it 

 i changed the data date also 

i will explain more i  updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021 

thats mean 15 days working day which give me increase at the total flot by -18 days  and if i decresed the remaning duration for certain activites the total flot increase also to become -20 

Member for

4 years 8 months

i,m updating it 

 i changed the data date also 

i will explain more i  updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021 

thats mean 15 days working day which give me increase at the total flot by -18 days  and if i decresed the remaning duration for certain activites the total flot increase also to become -20 

Member for

16 years 3 months

are you changing the data date also ?