Be reminded that activity interruptions can be multiple prior to data date [actual interruptions] as well as after data date [planned interruptions].
It is essential to keep the record straight for future claims if need be.
The Performance Archive or its P6 equivalent shall give you the details for interruptions before data date while the Calendar Exceptions or its P6 equivalent shall give you the details for planned interruptions.
Best Regards, Rafael
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2020-10-22 14:48
Member for
21 years 8 monthsBe reminded that activity
Be reminded that activity interruptions can be multiple prior to data date [actual interruptions] as well as after data date [planned interruptions].
It is essential to keep the record straight for future claims if need be.
The Performance Archive or its P6 equivalent shall give you the details for interruptions before data date while the Calendar Exceptions or its P6 equivalent shall give you the details for planned interruptions.
Best Regards, Rafael
Member for
16 years 3 monthsput the dates in the suspend
put the dates in the suspend and resume function in the status tab
and go to bars click remaining work bar then bar settings and check Under Bar necking Settings check activty nonwork intervals