Primavara Calendar Stopped Work (Covid 19)

Member for

21 years 8 months

Be reminded that activity interruptions can be multiple prior to data date [actual interruptions] as well as after data date [planned interruptions].

miltiple-interruptions

It is essential to keep the record straight for future claims if need be.

The Performance Archive or its P6 equivalent shall give you the details for interruptions before data date while the Calendar Exceptions or its P6 equivalent shall give you the details for planned interruptions.

Image-037



Image-038

Best Regards, Rafael

Member for

16 years 3 months

put the dates in the suspend and resume function in the status tab

and go to bars click remaining work bar then bar settings and check Under Bar necking Settings check activty nonwork intervals