Please be reminded that - "... there exists a common trend with Microsoft Project users which is quite common across the world. These schedulers simply ignore the requirement for proper planning logic and insert negative lags to achieve a quick programme with minimal activities".
Member for
16 years 3 monthsyes that is correct u have to
yes that is correct u have to run a couple global changes to de-staus a project and also change the data date
Member for
6 years 5 monthsThank you all for the useful
Thank you all for the useful information. I have found how to uncheck start and finish statuses. I initially did a globacl change to correct this.
Member for
21 years 8 monthshttps://www.planacademy.com/h
https://www.planacademy.com/how-to-remove-actuals-from-primavera-p6-schedule/
Please be reminded that - "... there exists a common trend with Microsoft Project users which is quite common across the world. These schedulers simply ignore the requirement for proper planning logic and insert negative lags to achieve a quick programme with minimal activities".
https://www.gbaprojects.com.au/uploads/files/whitepaper_-_poor_planning_negative_lag.pdf
You might need to adjust the logic of MSP schedules.
Member for
16 years 3 monthstake it into p6 and destatus
take it into p6 and destatus the project I sent u an email here I can send instructions on how to de-status
Member for
16 years 3 monthstake it into p6 and destatus
take it into p6 and destatus the project I sent u an email here I can send instructions on how to de-status