Importing a Microsoft Projects with Project Actuals Into P6 to compile a baseline

Member for

16 years 3 months

yes that is correct u have to run a couple global changes to de-staus a project and also change the data date 

Member for

6 years 5 months

Thank you all for the useful information. I have found how to uncheck start and finish statuses. I initially did a globacl change to correct this. 

Member for

21 years 8 months

https://www.planacademy.com/how-to-remove-actuals-from-primavera-p6-schedule/

Please be reminded that - "... there exists a common trend with Microsoft Project users which is quite common across the world. These schedulers simply ignore the requirement for proper planning logic and insert negative lags to achieve a quick programme with minimal activities".   

https://www.gbaprojects.com.au/uploads/files/whitepaper_-_poor_planning_negative_lag.pdf

You might need to adjust the logic of MSP schedules. 

Member for

16 years 3 months

take it into p6 and destatus the project I sent u an email here I can send instructions on how to de-status

Member for

16 years 3 months

take it into p6 and destatus the project I sent u an email here I can send instructions on how to de-status