Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-03-29 13:30 Permalink Try saving as an MPP then Try saving as an MPP then convert the MPP to an MPX then import the MPX add a column Check the Activity Type make sure that they are TASKS if not change the 1st one and do a fill down add a column Check the duration type make sure that they are fixed duration & units/time if not change the 1st one and do a fill down Also at the Projects level under defaults make sure that activity type is Task dependent Also at the Projects level under defaults make sure that duration type is fixed duration & units/time Also at the Projects level under calculations on the left hand side under activities make sure that Reset Remaining Duration and units to Original send me the file I will convert it for you. Check your email for my email address Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-03-29 13:30 Permalink Try saving as an MPP then Try saving as an MPP then convert the MPP to an MPX then import the MPX add a column Check the Activity Type make sure that they are TASKS if not change the 1st one and do a fill down add a column Check the duration type make sure that they are fixed duration & units/time if not change the 1st one and do a fill down Also at the Projects level under defaults make sure that activity type is Task dependent Also at the Projects level under defaults make sure that duration type is fixed duration & units/time Also at the Projects level under calculations on the left hand side under activities make sure that Reset Remaining Duration and units to Original send me the file I will convert it for you. Check your email for my email address
Member for
16 years 3 monthsTry saving as an MPP then
Try saving as an MPP then convert the MPP to an MPX then import the MPX
add a column Check the Activity Type make sure that they are TASKS if not change the 1st one and do a fill down
add a column Check the duration type make sure that they are fixed duration & units/time if not change the 1st one and do a fill down
Also at the Projects level under defaults make sure that activity type is Task dependent
Also at the Projects level under defaults make sure that duration type is fixed duration & units/time
Also at the Projects level under calculations on the left hand side under activities make sure that Reset Remaining Duration and units to Original
send me the file I will convert it for you. Check your email for my email address