XML Import to P6 - Durations affected

Member for

16 years 3 months

Try saving as an MPP then convert the MPP to an MPX then import the MPX

add a column Check the Activity Type make sure that they are TASKS if not  change the 1st one and do a fill down

add a column Check the duration type make sure that they are fixed duration & units/time if not  change the 1st one and do a fill down

Also at the Projects level under defaults make sure that activity type is Task dependent

Also at the Projects level under defaults make sure that duration type is fixed duration & units/time 

Also at the Projects level under calculations on the left hand side under activities make sure that Reset Remaining Duration and units to Original

send me the file I will convert it for you. Check your email for my email address