Did that and it worked. Apart from that I also right clicked on the Resource Spreadsheet and clicked on Spreadsheet Field from which I selected "Remaining Units".
Regards
Jithin
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2019-03-25 12:33
Member for
16 years 3 monthsof course it worked
of course it worked
Member for
14 years 7 monthsThanks Zoltan,Did that and it
Thanks Zoltan,
Did that and it worked. Apart from that I also right clicked on the Resource Spreadsheet and clicked on Spreadsheet Field from which I selected "Remaining Units".
Regards
Jithin
Member for
16 years 3 monthsview show on bottom resource
view show on bottom resource useage spreadsheet
on the right modify resource usage profile
right click spreadsheet fields remaining units
and make the time scale weeks
or
make sure your time scale is weeks
view show on bottom resource useage profile
on the right you rigth click and select resource usage profile options
on the data tab under display select units
and under that select remaining early
click on the graph tab and at the bottom check calculate average and base on hours per time period
the divide by interval should be 40 is viewiing for weeks.