Remaining Labor Unit by Week

Member for

16 years 3 months

of course it worked 

Member for

14 years 7 months

Thanks Zoltan,

Did that and it worked. Apart from that I also right clicked on the Resource Spreadsheet and clicked on Spreadsheet Field from which I selected "Remaining Units".

Regards

Jithin

Member for

16 years 3 months

view show on bottom resource useage spreadsheet

on the right modify resource usage profile

right click spreadsheet fields remaining units

and make the time scale weeks

or

make sure your time scale is weeks

view show on bottom resource useage profile 

 on the right you rigth click and select resource usage profile options

on the data tab under display select units

and under that select remaining early 

click on the graph tab and at the bottom check calculate average and base on hours per time period

the divide by interval should be 40 is viewiing for weeks.