Primavera Baseline used bu Acumen Fuse

Member for

20 years 11 months

Use the Assign Baseline command and select the respective file to be assigned as the Baseline:

[[wysiwyg_imageupload:5484:]]

You will see the Symbol B after the Name of your Project in Acumen.

[[wysiwyg_imageupload:5485:]]

Regards,

Andrew

Member for

11 years 10 months

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

Member for

11 years 10 months

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

Member for

16 years 3 months

I would assume that you have to tell Acumen what schedule the basline is. Depending on the version of p6 the baseline even though attached DOES NOT come along with p6 export.

My guess is that Acumen wil be using the Late start and late finish dates as baseline dates if a baseline is not provided or identified.