I would assume that you have to tell Acumen what schedule the basline is. Depending on the version of p6 the baseline even though attached DOES NOT come along with p6 export.
My guess is that Acumen wil be using the Late start and late finish dates as baseline dates if a baseline is not provided or identified.
Member for
20 years 11 monthsUse the Assign Baseline
Use the Assign Baseline command and select the respective file to be assigned as the Baseline:
[[wysiwyg_imageupload:5484:]]
You will see the Symbol B after the Name of your Project in Acumen.
[[wysiwyg_imageupload:5485:]]
Regards,
Andrew
Member for
11 years 10 monthsHiseems P15.2 doesnt export
Hi
seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen
Member for
11 years 10 monthsHiseems P15.2 doesnt export
Hi
seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen
Member for
16 years 3 monthsI would assume that you have
I would assume that you have to tell Acumen what schedule the basline is. Depending on the version of p6 the baseline even though attached DOES NOT come along with p6 export.
My guess is that Acumen wil be using the Late start and late finish dates as baseline dates if a baseline is not provided or identified.