Using Expected Finish Dates - A Simple Way to Update Schedules in Primavera P6

Member for

6 years 7 months

Also don't forget to update/check any existing expected finish dates during each update cycle, as the remaining duration will drive to zero if and when the data date equals the expected finish date on 'in-progress' activities.



to circumvent this when using expected finish dates, I run a global change to remove all expected finish dates from my scheudles following the progress update, that way any changes I make to the scheudle during the following cycle will flow through the logic and make the scheudle 'breath' properley.

Member for

7 years 1 month

Can I update the date in the current Finish Date field instead of inputting in the Expected Finish Date? If yes, will there be a difference?