Also don't forget to update/check any existing expected finish dates during each update cycle, as the remaining duration will drive to zero if and when the data date equals the expected finish date on 'in-progress' activities.
to circumvent this when using expected finish dates, I run a global change to remove all expected finish dates from my scheudles following the progress update, that way any changes I make to the scheudle during the following cycle will flow through the logic and make the scheudle 'breath' properley.
Member for
7 years 1 month
Member for7 years1 month
Submitted by ProjCtrlsBryan on Wed, 2019-03-13 05:24
Member for
6 years 7 monthsAlso don't forget to
Also don't forget to update/check any existing expected finish dates during each update cycle, as the remaining duration will drive to zero if and when the data date equals the expected finish date on 'in-progress' activities.
to circumvent this when using expected finish dates, I run a global change to remove all expected finish dates from my scheudles following the progress update, that way any changes I make to the scheudle during the following cycle will flow through the logic and make the scheudle 'breath' properley.
Member for
7 years 1 monthCan I update the date in the
Can I update the date in the current Finish Date field instead of inputting in the Expected Finish Date? If yes, will there be a difference?