Thanks Alexandre for this info, it is strange that the project calendar name is not mentioned in the task calendar column.

Best,

Moutaz

Member for

22 years 9 months

Mountaz,

"None" means that the task is using the project calendar; it is not necessary to assign the project calendar to tasks, except if you want the task calendar to manage a resource loaded task, instead of the resource calendar