Microsoft Project Member for 21 years 10 months Member for 21 years 10 months Submitted by moutaz aldeib on Sun, 2014-07-13 12:34 Permalink Thanks Alexandre for this Thanks Alexandre for this info, it is strange that the project calendar name is not mentioned in the task calendar column. Best, Moutaz Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2014-07-11 19:27 Permalink Mountaz,"None" means that the Mountaz, "None" means that the task is using the project calendar; it is not necessary to assign the project calendar to tasks, except if you want the task calendar to manage a resource loaded task, instead of the resource calendar Log in or register to post comments
Member for 21 years 10 months Member for 21 years 10 months Submitted by moutaz aldeib on Sun, 2014-07-13 12:34 Permalink Thanks Alexandre for this Thanks Alexandre for this info, it is strange that the project calendar name is not mentioned in the task calendar column. Best, Moutaz
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2014-07-11 19:27 Permalink Mountaz,"None" means that the Mountaz, "None" means that the task is using the project calendar; it is not necessary to assign the project calendar to tasks, except if you want the task calendar to manage a resource loaded task, instead of the resource calendar
Member for
21 years 10 monthsThanks Alexandre for this
Thanks Alexandre for this info, it is strange that the project calendar name is not mentioned in the task calendar column.
Best,
Moutaz
Member for
22 years 9 monthsMountaz,"None" means that the
Mountaz,
"None" means that the task is using the project calendar; it is not necessary to assign the project calendar to tasks, except if you want the task calendar to manage a resource loaded task, instead of the resource calendar