Open Project 1

Open Project 2

Use the New Window command on the view ribbon, select both projects on a Gantt chart view

Add predecessor link by clicking on 1st task, clicking on second task then using link icon

Beware

File names cant change or file server locations, this means its hard to maintain.  There are better more sophisticated ways to do this but above is the "out of the box" method.

Recommendation

Use Milestones in each schedule, avoid anything other than a FS +0 link.  Get PM or project 2 to drive the process, ensure the milestone is scoped clearly.

Member for

13 years 6 months

Dear Ron,

Thank you for your helpful information ;)

Member for

23 years 4 months

Open one project and using the subproject button open a second project at the bottom of the first project.  Select the task to  make the link between.   Save the projects and close them.    Version 2010