Seperating remaining duartion from % complete

Member for

22 years 9 months

Hello James,

you can't do that in MSP;

say you have a 6 day task, 50% complete; MSP calculates actual duration = 3 days, remaining duration = 3 days

when you enter a 4 days remaining duration because the task will be longer than expected, %complete becomes 43%

Alexandre