Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2012-05-04 09:54 Permalink Hello James,you can't do that Hello James, you can't do that in MSP; say you have a 6 day task, 50% complete; MSP calculates actual duration = 3 days, remaining duration = 3 days when you enter a 4 days remaining duration because the task will be longer than expected, %complete becomes 43% Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2012-05-04 09:54 Permalink Hello James,you can't do that Hello James, you can't do that in MSP; say you have a 6 day task, 50% complete; MSP calculates actual duration = 3 days, remaining duration = 3 days when you enter a 4 days remaining duration because the task will be longer than expected, %complete becomes 43% Alexandre
Member for
22 years 9 monthsHello James,you can't do that
Hello James,
you can't do that in MSP;
say you have a 6 day task, 50% complete; MSP calculates actual duration = 3 days, remaining duration = 3 days
when you enter a 4 days remaining duration because the task will be longer than expected, %complete becomes 43%
Alexandre