You can test it as follows:

- Just save 2 baselines: Baseline 1 and Baseline 2.

- Add any Project field for both Baseline 1 and Baseline 2 (e.g. Baseline 1 Duration and Baseline 2 Duration) to the table (e.g. Entry table of the Gantt Chart View).

- Practice and see how the fields change as you modify the task list by deleting, inserting, moving task lines.

Regards,

Ismet

Member for

14 years 3 months

Apologies saved two of these by accident!!! (won't happen again Mike, just realised that saving actually posts it!!!)