- Just save 2 baselines: Baseline 1 and Baseline 2.
- Add any Project field for both Baseline 1 and Baseline 2 (e.g. Baseline 1 Duration and Baseline 2 Duration) to the table (e.g. Entry table of the Gantt Chart View).
- Practice and see how the fields change as you modify the task list by deleting, inserting, moving task lines.
Member for
15 years 8 monthsYou can test it as follows:-
You can test it as follows:
- Just save 2 baselines: Baseline 1 and Baseline 2.
- Add any Project field for both Baseline 1 and Baseline 2 (e.g. Baseline 1 Duration and Baseline 2 Duration) to the table (e.g. Entry table of the Gantt Chart View).
- Practice and see how the fields change as you modify the task list by deleting, inserting, moving task lines.
Regards,
Ismet
Member for
14 years 3 monthsApologies saved two of these
Apologies saved two of these by accident!!! (won't happen again Mike, just realised that saving actually posts it!!!)