Microsoft Project Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Sat, 2009-08-08 18:00 Permalink RE: Decimal places in remaining duration field Thanks Rajesh, But Alex says it is fine. Stuart Member for 18 years 11 months Member for 18 years 11 months Submitted by rajesh anand on Sat, 2009-08-01 09:25 Permalink RE: Decimal places in remaining duration field Stuart, Send me the file to rajesh_anand70@yahoo.com I can do it for you Regards, Rajesh Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Tue, 2009-06-02 06:22 Permalink RE: Decimal places in remaining duration field Thanks Alex, i will try that in the next few weeks. Stuart Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2009-06-02 05:57 Permalink RE: Decimal places in remaining duration field Stuart, if your project is small, keu in again the task durations; if not, copy / paste the durations to a spreadsheet, then again to the duration comumn in MSP chance are that it will solve the problem if not, send me the project file to afaulxbriole@orange.fr Alexandre Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Tue, 2009-06-02 05:51 Permalink RE: Decimal places in remaining duration field Alex, i has the same duration. There are onlytwo claendars on this project. Thanks, Stuart Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2009-05-29 16:56 Permalink RE: Decimal places in remaining duration field Stuart, have you also checked calendar options? a standard day in calendars should have the same duration in hours as displayed in the options how many different calendars with different day templates do you have in your project? Alexandre Log in or register to post comments
Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Sat, 2009-08-08 18:00 Permalink RE: Decimal places in remaining duration field Thanks Rajesh, But Alex says it is fine. Stuart
Member for 18 years 11 months Member for 18 years 11 months Submitted by rajesh anand on Sat, 2009-08-01 09:25 Permalink RE: Decimal places in remaining duration field Stuart, Send me the file to rajesh_anand70@yahoo.com I can do it for you Regards, Rajesh
Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Tue, 2009-06-02 06:22 Permalink RE: Decimal places in remaining duration field Thanks Alex, i will try that in the next few weeks. Stuart
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2009-06-02 05:57 Permalink RE: Decimal places in remaining duration field Stuart, if your project is small, keu in again the task durations; if not, copy / paste the durations to a spreadsheet, then again to the duration comumn in MSP chance are that it will solve the problem if not, send me the project file to afaulxbriole@orange.fr Alexandre
Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Tue, 2009-06-02 05:51 Permalink RE: Decimal places in remaining duration field Alex, i has the same duration. There are onlytwo claendars on this project. Thanks, Stuart
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2009-05-29 16:56 Permalink RE: Decimal places in remaining duration field Stuart, have you also checked calendar options? a standard day in calendars should have the same duration in hours as displayed in the options how many different calendars with different day templates do you have in your project? Alexandre
Member for
21 years 9 monthsRE: Decimal places in remaining duration field
Thanks Rajesh,
But Alex says it is fine.
Stuart
Member for
18 years 11 monthsRE: Decimal places in remaining duration field
Stuart,
Send me the file to rajesh_anand70@yahoo.com
I can do it for you
Regards,
Rajesh
Member for
21 years 9 monthsRE: Decimal places in remaining duration field
Thanks Alex,
i will try that in the next few weeks.
Stuart
Member for
22 years 9 monthsRE: Decimal places in remaining duration field
Stuart,
if your project is small, keu in again the task durations; if not, copy / paste the durations to a spreadsheet, then again to the duration comumn in MSP
chance are that it will solve the problem
if not, send me the project file to afaulxbriole@orange.fr
Alexandre
Member for
21 years 9 monthsRE: Decimal places in remaining duration field
Alex,
i has the same duration. There are onlytwo claendars on this project.
Thanks,
Stuart
Member for
22 years 9 monthsRE: Decimal places in remaining duration field
Stuart,
have you also checked calendar options? a standard day in calendars should have the same duration in hours as displayed in the options
how many different calendars with different day templates do you have in your project?
Alexandre