Decimal places in remaining duration field

Member for

22 years 9 months

Stuart,

if your project is small, keu in again the task durations; if not, copy / paste the durations to a spreadsheet, then again to the duration comumn in MSP

chance are that it will solve the problem

if not, send me the project file to afaulxbriole@orange.fr

Alexandre

Member for

22 years 9 months

Stuart,

have you also checked calendar options? a standard day in calendars should have the same duration in hours as displayed in the options

how many different calendars with different day templates do you have in your project?

Alexandre