MS Project 2000 Finish Start Link

Member for

18 years

Thanks, but all of my start and end times are identical in the project, task, and resource calendars.

Member for

17 years 7 months

Hi Ben,



Have you been to the calendar options in the option menu? Here you can change the default settings of your calendar such as default starting time, default finish time etc..



Just go to TOOLS, OPTIONS, CALENDAR...



Maybe this helps..



Best regards,



Gerry


Member for

18 years

That’s what I am trying to do, but MS Project will not change the start or finish time in some instances. It’s a predessesor problem, but the predessesor finishes ends at the end of the day and shift, so there appears to be no issue.



Thank you for the help. Anyone else know what’s wrong?

Member for

24 years 5 months

Hi Benjamin,



Unfortumately, I did it task by task also when this happened to me. You may change the date format to hours to lessen the difficulty of doing it.



Good luck.



Se

Member for

18 years

Yeah something is going on with the constraint date where some tasks are starting at 5:00 pm when they should start at 8:00 AM and Finish at 8:00 PM or 8:00 AM when they should Finis at 5:00 PM.



I have a lot of Tasks how do I change this without going task by task? I already tried Find and Replace.

Member for

24 years 5 months

I too hate what you hate. What can we do?



Try checking the timescale in hours or change the date format with hours. It’s possible that the predecessor is finishing at 4PM while the successor is starting at 4:01PM of the same day.



Funny isn’t it? What do you expect from Mickey Mouse?

Good luck

Se



P.S. If this is the case, please don’t ask me why this is so, ask mickey mouse.