Have you been to the calendar options in the option menu? Here you can change the default settings of your calendar such as default starting time, default finish time etc..
Just go to TOOLS, OPTIONS, CALENDAR...
Maybe this helps..
Best regards,
Gerry
Member for
18 years
Member for18 years
Submitted by Benjamin Mora on Thu, 2008-04-03 13:02
Thats what I am trying to do, but MS Project will not change the start or finish time in some instances. Its a predessesor problem, but the predessesor finishes ends at the end of the day and shift, so there appears to be no issue.
Thank you for the help. Anyone else know whats wrong?
Yeah something is going on with the constraint date where some tasks are starting at 5:00 pm when they should start at 8:00 AM and Finish at 8:00 PM or 8:00 AM when they should Finis at 5:00 PM.
I have a lot of Tasks how do I change this without going task by task? I already tried Find and Replace.
Try checking the timescale in hours or change the date format with hours. Its possible that the predecessor is finishing at 4PM while the successor is starting at 4:01PM of the same day.
Funny isnt it? What do you expect from Mickey Mouse?
Good luck
Se
P.S. If this is the case, please dont ask me why this is so, ask mickey mouse.
Member for
18 yearsRE: MS Project 2000 Finish Start Link
Thanks, but all of my start and end times are identical in the project, task, and resource calendars.
Member for
17 years 7 monthsRE: MS Project 2000 Finish Start Link
Hi Ben,
Have you been to the calendar options in the option menu? Here you can change the default settings of your calendar such as default starting time, default finish time etc..
Just go to TOOLS, OPTIONS, CALENDAR...
Maybe this helps..
Best regards,
Gerry
Member for
18 yearsRE: MS Project 2000 Finish Start Link
Thats what I am trying to do, but MS Project will not change the start or finish time in some instances. Its a predessesor problem, but the predessesor finishes ends at the end of the day and shift, so there appears to be no issue.
Thank you for the help. Anyone else know whats wrong?
Member for
24 years 5 monthsRE: MS Project 2000 Finish Start Link
Hi Benjamin,
Unfortumately, I did it task by task also when this happened to me. You may change the date format to hours to lessen the difficulty of doing it.
Good luck.
Se
Member for
18 yearsRE: MS Project 2000 Finish Start Link
Yeah something is going on with the constraint date where some tasks are starting at 5:00 pm when they should start at 8:00 AM and Finish at 8:00 PM or 8:00 AM when they should Finis at 5:00 PM.
I have a lot of Tasks how do I change this without going task by task? I already tried Find and Replace.
Member for
24 years 5 monthsRE: MS Project 2000 Finish Start Link
I too hate what you hate. What can we do?
Try checking the timescale in hours or change the date format with hours. Its possible that the predecessor is finishing at 4PM while the successor is starting at 4:01PM of the same day.
Funny isnt it? What do you expect from Mickey Mouse?
Good luck
Se
P.S. If this is the case, please dont ask me why this is so, ask mickey mouse.