Part days of float

Member for

21 years 9 months

The problem was a number of lags with 1.25 days. Thanks again everyone.

Member for

21 years 9 months

Thanks everyone,



I will investigate these options now.



Stuart

Member for

24 years 6 months

There are many reasons why this may happen, but displaying the times with the date is the first step to resolving what is happening.



Then as Brian has indicated check that you default start and finish times are aligned with your calendars.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au


Member for

19 years 1 month

i guess it happens because of using percentage lags..?

Member for

18 years 4 months

Go into Tools | Options | View and pick a date format that shows the time.



It is possible that the Finish date of the task in question as a time on it that is not the same as the default end time for the calendar.

Member for

22 years 9 months

Stuart,

1. did you put a date constraint on one task?

2. did you change something in the calendars or calendar options?

Regards,

Alexandre