Microsoft Project Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Mon, 2007-06-18 06:11 Permalink RE: Part days of float The problem was a number of lags with 1.25 days. Thanks again everyone. Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Mon, 2007-06-18 04:23 Permalink RE: Part days of float Thanks everyone, I will investigate these options now. Stuart Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Sat, 2007-06-16 11:13 Permalink RE: Part days of float There are many reasons why this may happen, but displaying the times with the date is the first step to resolving what is happening. Then as Brian has indicated check that you default start and finish times are aligned with your calendars. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Sat, 2007-06-16 06:01 Permalink RE: Part days of float i guess it happens because of using percentage lags..? Member for 18 years 4 months Member for 18 years 5 months Submitted by Brian Ultican on Fri, 2007-06-15 14:39 Permalink RE: Part days of float Go into Tools | Options | View and pick a date format that shows the time. It is possible that the Finish date of the task in question as a time on it that is not the same as the default end time for the calendar. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2007-06-15 14:12 Permalink RE: Part days of float Stuart, 1. did you put a date constraint on one task? 2. did you change something in the calendars or calendar options? Regards, Alexandre Log in or register to post comments
Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Mon, 2007-06-18 06:11 Permalink RE: Part days of float The problem was a number of lags with 1.25 days. Thanks again everyone.
Member for 21 years 9 months Member for 21 years 9 months Submitted by Stuart Atkinson on Mon, 2007-06-18 04:23 Permalink RE: Part days of float Thanks everyone, I will investigate these options now. Stuart
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Sat, 2007-06-16 11:13 Permalink RE: Part days of float There are many reasons why this may happen, but displaying the times with the date is the first step to resolving what is happening. Then as Brian has indicated check that you default start and finish times are aligned with your calendars. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au
Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Sat, 2007-06-16 06:01 Permalink RE: Part days of float i guess it happens because of using percentage lags..?
Member for 18 years 4 months Member for 18 years 5 months Submitted by Brian Ultican on Fri, 2007-06-15 14:39 Permalink RE: Part days of float Go into Tools | Options | View and pick a date format that shows the time. It is possible that the Finish date of the task in question as a time on it that is not the same as the default end time for the calendar.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2007-06-15 14:12 Permalink RE: Part days of float Stuart, 1. did you put a date constraint on one task? 2. did you change something in the calendars or calendar options? Regards, Alexandre
Member for
21 years 9 monthsRE: Part days of float
The problem was a number of lags with 1.25 days. Thanks again everyone.
Member for
21 years 9 monthsRE: Part days of float
Thanks everyone,
I will investigate these options now.
Stuart
Member for
24 years 6 monthsRE: Part days of float
There are many reasons why this may happen, but displaying the times with the date is the first step to resolving what is happening.
Then as Brian has indicated check that you default start and finish times are aligned with your calendars.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Member for
19 years 1 monthRE: Part days of float
i guess it happens because of using percentage lags..?
Member for
18 years 4 monthsRE: Part days of float
Go into Tools | Options | View and pick a date format that shows the time.
It is possible that the Finish date of the task in question as a time on it that is not the same as the default end time for the calendar.
Member for
22 years 9 monthsRE: Part days of float
Stuart,
1. did you put a date constraint on one task?
2. did you change something in the calendars or calendar options?
Regards,
Alexandre