FIDIC Clause 20.1

Member for

19 years 10 months

Dear Mr. Tastro

Tahnk you very much for your further clarification. It is now very clear to me. Thanx a lot.

Best Regards - Tanveer

Member for

19 years 10 months

Hi Tanveer

That does not seem like "further particulars". The Engineer must request further particulars and he gets another 42 days to review it after submission.

Best regards

Mike Testro

Member for

19 years 10 months

Dear Mr. Tastro

Thank you for your reply. Further to my post, what if in the meeting / workshop the Engineer just a high level summary of the submitted claim.

Cheers - Tanveer

Member for

19 years 10 months

Hi Tanveer

If within the first 42 days the Engineer asks for further particulars then he has another 42 days after submission to study them.

He can then reject the claim within the 2nd 42 days.

It is possible that the engineer may request further particulars during a meeting / workshop.

Best regards

Mike Testro