That does not seem like "further particulars". The Engineer must request further particulars and he gets another 42 days to review it after submission.
Best regards
Mike Testro
Member for
19 years 10 months
Member for19 years10 months
Submitted by Tanveer Ahmad Niazi on Wed, 2013-07-03 09:25
Member for
19 years 10 monthsDear Mr. TastroTahnk you very
Dear Mr. Tastro
Tahnk you very much for your further clarification. It is now very clear to me. Thanx a lot.
Best Regards - Tanveer
Member for
19 years 10 monthsHi TanveerThat does not seem
Hi Tanveer
That does not seem like "further particulars". The Engineer must request further particulars and he gets another 42 days to review it after submission.
Best regards
Mike Testro
Member for
19 years 10 monthsDear Mr. TastroThank you for
Dear Mr. Tastro
Thank you for your reply. Further to my post, what if in the meeting / workshop the Engineer just a high level summary of the submitted claim.
Cheers - Tanveer
Member for
19 years 10 monthsHi TanveerIf within the first
Hi Tanveer
If within the first 42 days the Engineer asks for further particulars then he has another 42 days after submission to study them.
He can then reject the claim within the 2nd 42 days.
It is possible that the engineer may request further particulars during a meeting / workshop.
Best regards
Mike Testro