Actvitity Durations

Member for

19 years 10 months

Hi John

Your method of switching constraints with lead lags does not produce a dynamic critical path.

You have to ensure that when you delay a task all the successors must move accordingly.

This can only be done by using FS links exclusively.

Best regards

Mike Testro

Member for

14 years 3 months

Raymund, hit the nail on the head, thats exactly what it was thanks.

Member for

15 years 11 months

John,

Try to show the Date-Time in Dates columns, activities may have finish date in the morning and make sure the default calendar is the same as the calendars of your activities.

Hope this will help.