Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2012-02-27 10:57 Permalink Hi John Your method of Hi John Your method of switching constraints with lead lags does not produce a dynamic critical path. You have to ensure that when you delay a task all the successors must move accordingly. This can only be done by using FS links exclusively. Best regards Mike Testro Member for 14 years 3 months Member for 14 years 3 months Submitted by John Kelly on Mon, 2012-02-27 10:27 Permalink Raymund, hit the nail on the Raymund, hit the nail on the head, thats exactly what it was thanks. Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Mon, 2012-02-27 08:46 Permalink John, Try to show John, Try to show the Date-Time in Dates columns, activities may have finish date in the morning and make sure the default calendar is the same as the calendars of your activities. Hope this will help. Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2012-02-27 10:57 Permalink Hi John Your method of Hi John Your method of switching constraints with lead lags does not produce a dynamic critical path. You have to ensure that when you delay a task all the successors must move accordingly. This can only be done by using FS links exclusively. Best regards Mike Testro
Member for 14 years 3 months Member for 14 years 3 months Submitted by John Kelly on Mon, 2012-02-27 10:27 Permalink Raymund, hit the nail on the Raymund, hit the nail on the head, thats exactly what it was thanks.
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Mon, 2012-02-27 08:46 Permalink John, Try to show John, Try to show the Date-Time in Dates columns, activities may have finish date in the morning and make sure the default calendar is the same as the calendars of your activities. Hope this will help.
Member for
19 years 10 monthsHi John Your method of
Hi John
Your method of switching constraints with lead lags does not produce a dynamic critical path.
You have to ensure that when you delay a task all the successors must move accordingly.
This can only be done by using FS links exclusively.
Best regards
Mike Testro
Member for
14 years 3 monthsRaymund, hit the nail on the
Raymund, hit the nail on the head, thats exactly what it was thanks.
Member for
15 years 11 monthsJohn, Try to show
John,
Try to show the Date-Time in Dates columns, activities may have finish date in the morning and make sure the default calendar is the same as the calendars of your activities.
Hope this will help.