Asta Powerproject Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2017-06-01 17:35 Permalink Hi Dan - Welcome to planning Hi Dan - Welcome to planning plannet. Right Click on the top of the duration column. Select Table definition Select duration in the dropdown In the right hand panel find Overide Time Unit and select the one you want. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2017-06-01 17:35 Permalink Hi Dan - Welcome to planning Hi Dan - Welcome to planning plannet. Right Click on the top of the duration column. Select Table definition Select duration in the dropdown In the right hand panel find Overide Time Unit and select the one you want. Best regards Mike Testro
Member for
19 years 10 monthsHi Dan - Welcome to planning
Hi Dan - Welcome to planning plannet.
Right Click on the top of the duration column.
Select Table definition
Select duration in the dropdown
In the right hand panel find Overide Time Unit and select the one you want.
Best regards
Mike Testro